Entergy Mississippi was awarded $4.2 million by the U.S. Department of Energy (DOE) through the SPARK initiative, to upgrade power grids throughout multiple states. The project is expected to bring a 25% increase to power grid efficiency and upgrade to about 375 miles of transmission lines across Mississippi.

Kristen Kaylor
Entergy Mississippi receives $4.2 million to upgrade power infrastructure for customers
Haley Fisackerly, President and CEO of Entergy Mississippi, said the partnership with the Department of Energy will allow the company to use modernized technology to upgrade power systems faster and make electricity cheaper for customers.
“What it allows us to do is to take our existing transmission grid and deploy new technologies that will allow it to improve the capacity and way it delivers power more efficiently, more effectively, and avoid costly transmission upgrades that have a huge impact on our customers,” Fisackerly said.
DOE Office of Electricity Assistant Secretary Katie Jereza spoke about the partnership. She said the SPARK initiative will upgrade over 1,500 miles of electricity infrastructure nationwide.
“Meeting America's growing electricity needs is not just about producing more power, it's about increasing the capacity to deliver it,” Jereza said.
Entergy Mississippi currently serves 459,000 customers across 45 counties. Fisackerly said a benefit of the technology being used for upgrades is that customers will not face outages during project work.
Jeremy Loving, a resource planning engineer for the project, said the partnership between Entergy Mississippi and the U.S. Department of Energy allows for new technology that will save time on rebuilding and upgrades.
“If we're doing transmission line upgrades, this would take years to accomplish. What we're able to do with dynamic line ratings is we can get them manufactured and deployed without causing any outages into the service territory within a week's time,” Loving said. “...this could be cutting down from five to six years for larger transmission upgrades to eight to 12 months.”
Tim Sansing, another engineer on the project, said one of the tools being used in this project is known as dynamic line ratings. Ratings collect data such as wind speeds, temperature and other factors to determine how much power can be efficiently pushed through transmission lines.
"You've got wind speed, solar radiation, conductor temperature, ambient temperature,” Sansing said. “So, you're getting a lot of different data that you can use to better understand what you can push through the conductor.”
Sansing said having this technology will help save millions of dollars on operations and building costs.
There is not a set time when upgrades will officially begin, but the project is expected to be finished within a year once it starts.